Industrial Equipment  ·  3P Use Case

3P Production Preparation:
Industrial Equipment Manufacturer

Full 3P implementation on a new production line — Seven Flows analysis, 7-Ways workshop, moonshine prototyping, continuous flow design, and complete physical line standup. Delivered alongside simultaneous new line construction.

7Flows Mapped
7Design Alternatives Per Step
0Existing Line to Copy From
The Challenge

A New Line. Built Once. No Margin for Error.

An industrial equipment manufacturer needed to stand up a new assembly line for a new product family — large, configurable units with long build sequences and heavy components. The challenge: the traditional line design approach would have locked in inefficiency from first production. Once the line is built, the layout is fixed, the flow is fixed, and the cycle time is fixed — for years.

The client needed to design the right line before breaking ground. That requires a methodology specifically built for that problem. Nextep deployed 3P — Production Preparation Process — the only tool designed from first principles for exactly this situation.

This use case shows how Nextep runs 3P on a new line: the sequence, the tools, and the decisions that matter before anything is bolted to the floor.

Why 3P

First Principles.
Not Inherited Waste.

3P starts with a clean sheet. It forces the design team to question every assumption about how production should flow before any physical infrastructure is committed. Seven Flows analysis maps all flows through the process — people, material, information, machine, process, quality, and safety.

Then the team generates seven alternative production concepts for every major step. Seven — not two or three. The discipline of generating seven forces creative thinking and surfaces options that conventional design never considers.

Moonshine prototyping builds cardboard and PVC mock-ups to test flow, reach, and ergonomics before spending a dollar on real equipment. Problems found in the prototyping phase cost almost nothing to fix. Problems found after installation cost everything.

The 3P Process

How 3P Works

01
Seven Flows Analysis
Map every flow through the process — people, material, information, machine, process, quality, safety. Identify which flows conflict and where waste is baked in by design.
02
7-Ways Workshop
Generate seven alternative production concepts for every critical process step. Forces creative thinking. Surfaces non-obvious solutions conventional design never reaches.
03
Moonshine Prototyping
Cardboard and PVC mock-ups of the proposed line. Test flow, reach, ergonomics, and operator movement before committing to equipment. Find problems when they're cheap to fix.
04
Takt Time Design
Size every station to customer demand. Balance the line so no step is over-designed and no step becomes a bottleneck from day one.
05
Standard Work Development
Operator instructions, sequence, timing, and quality checks developed before first production. The line is documented before it runs, not after.
06
Physical Line Standup
Nextep leads the physical standup of the line — layout, equipment placement, flow verification, and operator training. From design to first unit.
What 3P Locks In

Lean by Design.
Every Unit. Permanently.

When the line is designed with 3P, the flow, the station balance and the standard work are built in before first production. That gain is permanent — it's built into the line. Every unit produced from day one captures it. This isn't a one-time event. It's the foundation every future unit is built on.

7Flows designed in
63P phases, design to first unit
∞Units that capture the gain
When to Use 3P

3P Is for One Moment.

3P is the right methodology for exactly one moment: before a new line is built, or before a radical process redesign is committed. Once equipment is in place, once the layout is fixed, once production is running — you're optimizing around inherited constraints. 3P eliminates those constraints before they exist.

If you're planning a new production line, adding capacity, or redesigning a process from the ground up, that's the moment for 3P. Nextep has led full 3P deployments in industrial manufacturing and packaging. The methodology works wherever flow matters — which is everywhere.